Track construction project cash balances across payment periods
Enter starting cash and the receipts and costs for each period to see ending balances and the largest period-end shortfall. This reveals whether planned customer receipts keep up with project spending at the selected reporting intervals.
Running project cash-balance formula
Period net cash = receipts − costs. Ending balance = previous balance + period net cash. Peak funding need = max(0, −lowest ending balance including starting cash).
Worked example
Start with $5,000 cash. Period one receives $10,000 and spends $18,000, ending at −$3,000. Period two receives $15,000 and spends $10,000, ending at $2,000. Period three receives $20,000 and spends $12,000, ending at $10,000. The lowest balance is −$3,000, so the period-end funding need is $3,000.
Common estimating pitfalls
- Period-end balances can miss larger shortfalls within a period.
- Cash receipts and payments are not the same as accounting revenue and profit.
Frequently asked questions
Does a positive ending balance mean the job is profitable?
No. Cash timing depends on deposits and when costs are paid. Review job profitability separately using revenue and complete costs.
How can I check intramonth funding gaps?
Use shorter periods or a dated transaction forecast. This calculator only evaluates balances at the ends of the entered periods.
What does peak funding need represent?
It is the additional cash needed to keep the modeled starting and period-end balances from going below zero, based on the receipts and costs entered.