Overhead recovery calculator

Put annual operating costs against the work that carries them. Compare two ways to allocate overhead to one job.

01 / Inputs

Use your project numbers

Use the same annual period for overhead, direct costs, and billable hours. Do not include overhead already built into a labor billing rate in the direct-cost inputs.

02 / Estimate

Your working numbers

Ready when you are.

Review the example inputs, then calculate to see the quantities and cost breakdown.

How the math works

Cost-based rate = annual overhead ÷ annual direct costs × 100. Cost-based job allocation = job direct costs × that rate (as a decimal). Hourly recovery = annual overhead ÷ annual billable hours; hours-based job allocation = job billable hours × hourly recovery.

Overhead allocation is not profit. Confirm which costs are already included in your labor or direct-cost rates before applying either approach.

Planning estimate only. Verify site measurements, material specifications, supplier pricing, labor rates, taxes, codes, and project conditions before bidding or building.

Contractor field notes

Allocate company overhead to a construction job

This calculator compares two methods of recovering annual overhead: as a percentage of annual direct costs, or as a cost per billable hour. It then applies each rate to the job inputs so you can choose a consistent allocation method.

Job overhead allocation formulas

Cost-based overhead rate = annual overhead ÷ annual direct costs. Hourly overhead rate = annual overhead ÷ annual billable hours. Multiply the selected rate by job direct costs or job billable hours.

Worked example

With $120,000 annual overhead, $600,000 annual direct costs, and 4,000 billable hours, the rates are 20% of direct cost and $30 per billable hour. A job with $25,000 direct costs and 150 billable hours receives $5,000 overhead by cost or $4,500 by hours. These are alternatives, not a combined $9,500 charge.

Common estimating pitfalls

  • Use annual direct costs for this percentage, not annual revenue.
  • Keep the chosen allocation method consistent with the rest of your estimate.

Frequently asked questions

Why do the two methods give different results?

A job’s share of company direct costs may differ from its share of company labor hours. Material-heavy and labor-heavy jobs can therefore recover different overhead amounts.

Should I add both overhead results to my price?

No. The results compare alternative allocation methods for the same company overhead.

What if expected billable hours change?

Update the annual hours estimate. Fewer billable hours increase the amount of overhead each hour needs to recover.