Contractor field notesHow This Calculator WorksFormula, worked example, assumptions, common pitfalls, and FAQs
Check both debris volume and hauling weight
Different demolition materials have very different densities and bulking factors. Calculate each material separately, sum debris volume and material mass, and use whichever dumpster capacity constraint needs more loads. Ordinary debris rates must not be used for hazardous or regulated waste.
Debris, mass, and dumpster requirements
Original volume = area × thickness, or entered volume. Debris volume = original volume × bulking factor. Weight = original volume × density. Loads = max(ceiling(debris volume ÷ volume capacity), ceiling(weight ÷ weight allowance)).
Worked example
A 300 sq ft concrete slab at 4 inches thick contains 100 cu ft. At 150 lb/cu ft, it weighs 15,000 lb, or 7.5 short tons. A 1.5 bulking factor produces 5.56 cu yd of debris. A 10 cu yd dumpster with a 4-short-ton allowance needs one load by volume but two by weight, so use two loads.
Assumptions and common pitfalls
- Bulking increases loose volume, not material mass.
- Dumpster capacity and weight allowance must come from the hauling provider.
- Asbestos, lead-containing waste, and other hazardous materials are excluded.
Frequently asked questions
What is a bulking factor?
It is loose debris volume divided by original in-place material volume. A factor of 1.5 means 50% more volume after demolition. It does not increase the estimated weight.
Which ton unit does the calculator use?
Imperial mode uses US short tons of 2,000 pounds. Metric mode uses metric tonnes of 1,000 kilograms. The output labels identify which one applies.
Are disposal and hauling the same cost?
No. Disposal can be priced per weight or per load, while hauling is separately priced per required load. Check supplier inclusions to avoid counting a bundled service twice.