Illustrative educational example only. This is not a completed Taplin Systems project or customer case study. Verify dimensions, site conditions, product specifications, current quotes, and local requirements before using a result.
Scenario: A 675-square-foot existing concrete patio is removed and replaced. The volume example assumes a 4-inch new slab and a separately stated 10% order allowance.
Published
Last updated
01
Start with the measured area and slab assumption
The area is 675 square feet. For this example only, assume a 4-inch slab thickness. Convert 4 inches to one-third of a foot, multiply by the area, then divide cubic feet by 27 to convert to cubic yards.
At that stated thickness, the base volume is about 8.33 cubic yards. Adding the example's 10% allowance gives about 9.17 cubic yards; the Concrete Calculator rounds its recommended order up to the next quarter yard, or 9.25 cubic yards. Confirm supplier increments, minimums, access, and placement conditions. A different measured thickness changes the result directly.
02
Separate removal, preparation, and new work
A replacement estimate should list demolition and disposal separately from the new slab. Confirm the existing slab thickness and reinforcement, access for equipment, haul distance, disposal rules, subbase work, forms, reinforcement, joints, concrete mix, delivery, placement, and cleanup.
Do not infer debris weight from volume without a suitable material and site assumption. Check the actual disposal provider's container volume and weight limits, and account for any local disposal requirements.
- Measure the actual patio and verify thickness in the field.
- Use the selected mix, reinforcement, subbase, and finish specifications.
- Obtain current concrete, delivery, demolition, and disposal quotes.
03
Compare finish choices using real quotes
A broom finish and a decorative finish can have different labor, material, preparation, and schedule requirements. Compare them as separate estimate options using quotes for the actual products and crew scope; this example does not invent local prices.
After entering the verified costs, review the project total and target margin in the Estimator Builder. Keep overhead and contingency distinct from material waste and contractor profit.