Scenario: A 64-linear-foot, 4-foot-high straight fence run with pressure-treated posts, redwood rails, hog-wire infill, and one 3-foot gate.

Published

Last updated

01

Example inputs and assumptions

This is a teaching example, not a completed Taplin Systems project or a recommended fence design. To show how the calculator responds, it assumes the gate is centered in one straight 64-foot run, posts are spaced 8 feet apart, each section has two rails, hog-wire panels are 8 feet wide, and the post holes are 12 inches in diameter by 24 inches deep.

The material calculation also uses a 10% waste allowance and a concrete-bag yield of 0.6 cubic feet. Actual post spacing, gate location, hole size, panel width, waste, and bag yield must match the site, product instructions, and applicable requirements.

  • Fence height: 4 feet
  • Gate: one 3-foot opening, centered for this example
  • Post spacing: 8 feet
  • Rails: two per section
  • Hog-wire panel width: 8 feet
  • Post holes: 12 inches wide by 24 inches deep
  • Waste allowance: 10%

02

How the takeoff quantities are calculated

The gate divides the run into two 30.5-foot fence segments. At 8-foot spacing, each segment rounds up to four sections, for eight sections total. The automatic layout count is 10 posts, including the two gate posts.

Two rails per section gives 16 rail pieces before waste; with 10% waste the calculator rounds that allowance up to 18 pieces. The two segments require eight 8-foot hog-wire panels before waste, or nine panels after the stated allowance.

Ten cylindrical holes at the stated dimensions contain about 15.71 cubic feet of concrete. Dividing by the assumed 0.6-cubic-foot bag yield and rounding up gives 27 bags. These quantities are planning outputs, not a structural design or optimized cut plan. Check actual lumber lengths, panel coverage, corner conditions, bracing, and gate hardware before ordering.

03

Labor, overhead, and selling price

Enter labor hours and the employer cost per labor hour, plus any equipment, disposal, material, gate, and hardware costs supported by current project quotes. This example does not publish market prices.

The Fence Calculator's selling-price result applies the entered target margin to its modeled materials, labor, equipment, and disposal costs. It does not add a separate company-overhead allocation. If overhead is not already included in those inputs or rates, calculate it separately, include it once in the cost basis, and then price the complete cost basis for the intended margin.

  • Avoid counting the same overhead in both a labor rate and a separate allocation.
  • Use current supplier quotes and confirm stock lengths and package quantities.
  • Check local rules, site conditions, utility locations, and product requirements before construction.